Information on road infrastructure projects in Karabakh, Eastern Zangazur revealed

The State Agency of Azerbaijan Automobile Roads has disclosed information about road infrastructure projects being implemented in the Karabakh and East Zangazur economic regions, SİA informs via the agency.

The work is currently ongoing on the design and construction of 45 automobile roads with a total length of 3,382.6 km to restore road infrastructure in the liberated territories, as part of the "First State Program for the Great Return to the liberated territories" and based on orders from President Ilham Aliyev.

To date, construction has been fully completed on 7 automobile roads with a total length of 315.9 km, and 1 project has been partially completed (24.2 km out of 39.7 km of the Shukurbayli-Jabrayil-Hadrut road).

Construction completion for 16 projects is planned for 2025-2026. Additionally, work is being carried out on the construction of internal roads in 8 cities, roads leading to 8 villages, and 6 inter-district automobile roads.

The total length of tunnels (45 tunnels) being built on automobile roads in the liberated territories is 70.8 km, 447 bridges - 9,581.6 m, and 16 viaducts - 3,871 m.

Currently, construction has been completed on 28 tunnels (59.6 km), 392 bridges (8,339.1 m), and 9 viaducts (1,695 m).